HomeMy WebLinkAboutPW13-208 - Change Order - #1 - SCI Infrastructure, LLC - SR 516 to S 231st Way Levee Improvements - 01/24/2014 � <v
Records M ap g e m le
KENT Document,
WASHIHGTON
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: SCI Infrastructure, LLC
Vendor Number:
JD Edwards Number Contract Number: VW 13 Orapg
This is assigned by City Clerk's Office
Project Name: SR 516 to S 231't Way Levee Improvements
Description: ❑ Interlocal Agreement ❑ Change Order ❑ Amendment ® Contract
❑ Other:
Contract Effective Date: 9/3/2013 Termination Date:
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Jason Bryant Department: PW - Engineering
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #1
5•Publlc\RecordsManagement\Forms\ContractCover\adcc7832 1 11/08
KENT
W R 5 H I N G T O N
CHANGE ORDER NO. 1
NAME OF CONTRACTOR: SCI Infrastructure, LLC ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SR 516 to S 231s' Way Levee Improvements
ORIGINAL CONTRACT DATE: 9/3/2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Repair side slopes, rain event caused damage to unestablished side
slopes.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $583,462.54
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0
(incl. applicable WSST)
Current Contract Amount $583,462.54
(incl. Previous Change Orders)
Current Change Order $194,059.46
Applicable WSST Tax on this Change $18,435.65
Order
Revised Contract Sum $795,957.65
CHANGE ORDER - 1 OF 3
Original Time for Completion 60 working days
(Insert date)
Revised Time for Completion under 60 working days
prior Change Orders
(insert date)
Days Required (f) for this Change 30 working days
Order
Revised Time for Completion 90working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below. j
pe
CONTRACTOR: CITY OF KENT:
4 W
By: B(signatu/ )17 (si ture
J SGz
Print me: e Cc61- _
[� -
It U N"1 RA-r;"(_M Jfttj 6137i'le— Its
(title) ( t!e)
DATE: O 1 — D 7 'l DATE:
CHANGE ORDER - 2 OF 3
I
i
APPROVED AS TO F RM:
(app/icab! f Mayor's gnature equ red)
Kent Law Departmen
1
CHANGE ORDER - 3 OF 3
FILE 200 2
��
[CENT CHANGE ORDER WORKSHEET
KVE= i
Date of change order: Date worked performed:
12- - �1-13 �L �z—I t
Concurrence/Approval(Intls&Date): Construction Supervisor Construction Manage
Project Name: �/Z �P �! T07 2�/ ����/z'r'= Project Number: '��
Contractor: 4
C.O. Type/Bid Item#: Force Account (est. total) $ Lump Sum$
Schedule#: Change Order#: -
Ordered By.; • ?'-i�� Engineer . T%e, Contractor c-SG--7—
Description of Work: R t zpo r
((�� f
Reason: 4cA t 5eJ vary r� PU?-n,�-� I ndGP TO
Li ✓l e,6-Fn b I I s G�i L I cl P, 'L) tJc'S .
COST ESTIMATE
X $ / = $
QUANTITY PRICE UNIT(S) ESTIMATED TOTAL
ACTUAL COST 1vi4,ors 9 4(p
X $ _ $
QUANTITY PRICE UNIT(S) ACTUAL TOTAL
TIME
Extension Of Contract Time Due To This Change Order------------------ rkmg 6ays5fe
COMMENTS
Posted by Date Checked by Date Pay Estimate#
UVT\PWPublic\CheckOut\CoiutructioiiToms-Public ProlectsTay Estmuate FomulCbange Order Worksiieetdoc
Ree 5/21103
Date Amount
2-Oct 7210.41
3-Oct 1288151
4-Oct 2501457
5-Oct 19510.48
10-Oct 961979
11-Oct 944386
14-Oct 680511
15-Oct 16436.06
16-Oct 6966.69
17-Oct 500568
18-Oct 6091.47
19-Oct 3092.71
20-Oct 477188
21-Oct 5805.41
22-Oct 171555
24-Oct 5431.69
25-Oct 2253765
25-Oct 1715.55
25-Oct 2900
28-Oct 2870.33
30-Oct 4188.07
31-Oct 46413
1-Nov 333574
4-Nov 3723.82
5-Oct 2344.13
Total 194059.46
P1�
FA Sheet No 1
DAILY REPORT OF
FORCE ACCOUNT WORKED �--- ENT
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date- 101212013
Description of Work R&R plastic, Dig out bad soils,fix cracks in soil
Work by Subcontraclor7 No
Prime Contractor SCI Sub-Contractor
LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 7 5 628 $ 471 00
Lyle B Operator Excavator 75 6051 $ 45383
Shane W Operator Excavator 5 5 6051 $ 33281
Dennis C Foreman 75 628 $ 471 00
Almaiden E I Pipe layer 55 4898 $ 26939
SUBTOTAL-LABOR $ 1,99803
LABOR OVERHEAD&PROFIT @ 29% $ 57943
LABOR TOTAL $ 2,57746
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Deschplion Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 75 2873 $ 21548
335-104/121 GMC Truck 15 1646 $ 24690
220-143 300 excavator 55 17943 $ 98687
205-141 JD 310 backhoe 55 3889 $ 21390
202-104 Yanmar Mini 55 2517 $ 13844
SUBTOTAL-EQUIPMENT $ 1,80159
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 37833
EQUIPMENT TOTAL $ 2,17992
MATERIALS/SERVICES/RENTALS
MATERIALS I SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Bobcat rental 55 hrs $ 3769 $ 20730
T barger 8 hrs $ 130 00 $ 1,04000
Carbon Canyon 6 hrs $ 13000 $ 78000
$
$
SUBTOTAL $ 2,02730
OVERHEAD&PROFIT @ 21% $ 425 73
TOTAL $ 2,45303
Verification of Hours Worked TOTAL $ 7,21041
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEETTOTAL• $ 7,210.41
Owner's Representative Date
I
Pay Estimate Entered
Date
By
FA Sheet No • 2
DAILY REPORT OF
FORCE ACCOUNT WORKED --''KE,T
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/3/2013
Description of Work Excavate material out of slope, 280 yds removed
112 If of slope removed 14 T&T loads
Work by Subcontractor? NO
Prime Contractor SCI Sub-Contractor
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION His Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 8 628 $ 50240
Lyle B Operator Excavator 8 60 51 $ 48408
Kellyb/Lloyd M Truck Driverr 145 5483 $ 79504
Dennis C Foreman 8 62 8 $ 50240
Dominic E Pipe layer 8 4898 $ 39184
SUBTOTAL-LABOR $ 2,67576
LABOR OVERHEAD&PROFIT @ 29% $ 77597
LABOR TOTAL $ 3,451 73
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 8 2873 $ 22984
335-1041121 GMC Truck 16 1646 $ 26336
220-143 300 excavator 8 17943 $ 1,43544
205-141 JD 310 backhoe 8 3889 $ 311 12
Dump Truck and trailer 145 9541 $ 1,38345
SUBTOTAL-EQUIPMENT $ 3,62321
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 76087
EQUIPMENT TOTAL $ 4,38408
MATERIALS/SERVICESIRENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Export 14 loads $ 7500 $ 1.05000
Carbon Canyon 24 hrs $ 13000 $ 3,12000
$
SUBTOTAL $ 4,17000
OVERHEAD&PROFIT @ 21% $ 87570
TOTAL $ 5,04570
Verification of Hours Worked TOTAL $ 12,881 51
12%MARKUP (for prime when
subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 12,881.51
Owner's Representative Date
Pay Estimate Entered
Date
By
r
FA Sheet No , 3
DAILY REPORT OF
FORCE ACCOUNT WORKED >_ T
Project Name SR 516 to 231st Levee Project No 09:3006
Item No Date 10/8/2013
Description of Work Excavate material out of slope,280 yds removed
242 If of slope removed 37 T&T loads
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor
LABOR . "' ?> •� � �+# tsx �.
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 8 628 $ 50240
Lyle B Operator Excavator 8 6051 $ 48408
Kelly/Lloyd/Alan/Jerry Truck Driverr 265 5483 051 7307 $ 1,48953
Dennis C Foreman 8 628 1 8483 $ 58723
Dominic E Pipe layer 8 4898 1 1 $ 391 84
SUBTOTAL-LABOR $ 3,45508
LABOR OVERHEAD&PROFIT @ 29% $ 1,001 97
LABOR TOTAL $ 4,45705
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 8 2873 $ 22984
3 3 5-1 0411 2 1 GMC Truck 16 1646 $ 26336
220-143 300 excavator 8 17943 S 1,43544
205-141 JD 310 backhoe 8 3889 S 311 12
Dump Truck and trailer 27 9541 $ 2,57607
SUBTOTAL-EQUIPMENT $ 4,81583
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 1,01132
EQUIPMENT TOTAL $ 5,82715
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units I UnitPrlce DOLLARAMOUNT
Export 37 loads $ 7500 $ 2,77500
Carbon Canyon 48 hrs $ 13000 $ 6,24000
Mini excavator 8 hrs $ 2517 $ 201 36
T barger 8 hrs $ 13000 $ 1,04000
RL Clearing 1475 hrs $ 13000 $ 1,91750
SUBTOTAL $ 12,173 86
OVERHEAD&PROFIT @ 21% $ 2,55651
TOTAL $ 14,730 37
Verification of Hours Worked TOTAL $ 25,014 57
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEET TOTAL' $ 25,014.57
Owner's Representative Date
Pay Estimate Entered
Date
By
FA Sheet No : 4
DAILY REPORT OF
FORCE ACCOUNT WORKED `--/ _ T
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/9/2013
Description of Work Excavate material out of slope,320 yds removed
89 If of slope removed 15T&T loads
Work by Subcontractor'? NO
Prime Contractor SCI Sub-Contractor
a „ant• , xv� LABOfZ -" ,_ • tW
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 5 628 $ 31400
Lyle/Kenny/Shane Operator Excavator 24 6051 $ 1.45224
Kelly/Lloyd/Jerry Truck Driverr 225 5483 $ 1,23368
Dennis C Foreman 8 628 $ 50240
Dominic E Pipe layer 8 4898 $ 391 84
SUBTOTAL-LABOR $ 3,894 16
LABOR OVERHEAD&PROFIT @ 29% $ 1,12931
LABOR TOTAL $ 5,02347
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 8 7873 $ 22984
3 3 5-1 0 411 2 1 GMC Truck 16 1646 $ 26336
220-143 300 excavator 8 17943 $ 1,43544
205-141 JD 310 backhoe 8 3889 $ 31112
Dump Truck and trailer 65 9541 $ 62017
SUBTOTAL-EQUIPMENT $ 2,85993
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 60059
EQUIPMENT TOTAL $ 3,46052
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Export 15 loads $ 7500 $ 1,12500
Carbon CanyonfT barger/RL clearing 535 hrs $ 13000 $ 6,95500
Mini excavator 8 hrs $ 2517 $ 20136
Bomag Roller 8 hrs $ 41 88 $ 33504
D%Dozer 8 hrs $ 62 05 1 $ 49640
SUBTOTAL $ 9,11280
OVERHEAD&PROFIT @ 21% $ 1,91369
TOTAL $ 11,026 49
Verification of Hours Worked TOTAL $ 19,510 48
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEET TOTAL- $ 19,510.48
Owner's Representative Date
Pay Estimate Entered
Date
By
FA Sheet No. 5
DAILY REPORT OF
FORCE ACCOUNT WORKED -- ENT
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 1 011 0/20 1 3
Description of Work Import Screenings, Place in slope
Work by Subcontractors No
Prime Contractor SCI Sub-Contractor
p,x��rr_m•���,- . :�;nc��,�"�;� �s'-LABOR �.�-�., '` �-��i.
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 628 $
Lyle/Kenny/Shane Operator Excavator 6051 $
Kelly/Lloyd/Jerry Truck Driverr 24 5483 is 7307 $ 1,42553
Dennis C Foreman 62 8 $ -
Dominic E Pipe layer 4898 $ -
SUBTOTAL-LABOR $ 1,42553
LABOR OVERHEAD&PROFIT @ 29% $ 41340
LABOR TOTAL $ 1,83893
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 2873 $
335-104/121 GMC Truck 1646 $
220-143 300 excavator 17943 $
205-141 JD 310 backhoe 3889 $ -
Dump Truck and trailer 255 9541 $ 2,43296
SUBTOTAL-EQUIPMENT $ 2,43296
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 51092
EQUIPMENT TOTAL $ 2,94388
MATERIALS/SERVICES/RENTALS
MATERIALS SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Export loads $ 7500 $ -
Carbon Canyon/T barger/RL clearing 3075 hrs $ 13000 $ 3,99750
Mini excavator hrs $ 25 17 $ -
Bomag Roller hrs $ 4188 $
D%Dozer Jhrs I $ 6205 $ -
SUBTOTAL $ 3,99750
OVERHEAD&PROFIT @ 21% $ 83948
TOTAL $ 4,83698
Verification of Hours Worked TOTAL $ 9,61979
12%MARKUP (for prime when
subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 9,619.79
Owner's Representative Date
Pay Estimate Entered
Date
By
FA Sheet No 6
DAILY REPORT OF
FORCE ACCOUNT WORKED _ T
Project Name SR 616 to 231st Levee Project No 09,3006
Item No Date 1 011 1/20 1 3
Description of Work Import Screenings, Place In slope
Remove unsuitable
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor
f�,:
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 6 628 $ 37680
Lyle/Kenny/Shane Operator Excavator 18 6051 $ 1,08918
Kelly/Lloyd/JerryTruck Dnverr 5483 $ -
Dennis Foreman 6 628 $ 37680
Dominic E Pipe layer 6 48 98 $ 29388
SUBTOTAL-LABOR $ 2,13666
LABOR OVERHEAD&PROFIT @ 29% $ 61963
LABOR TOTAL $ 2,75629
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 61 2873 $ 17238
335-104/121 GMC Truck 12 1646 $ 19752
220-143 300 excavator 6 17943 $ 1,076 58
205-141 JD 310 backhoe 6 3889 $ 23334
Dump Truck and trailer 9541 s -
SUBTOTAL-EQUIPMENT $ 1,67982
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 352 76
EQUIPMENTTOTAL $ 2,03268
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLARAMOUNT
Export 5 loads $ 7500 $ 37500
Carbon Canyon/T barger/RL clearing 2075 hrs $ 13000 $ 2,69750
Mini excavator/Bomag Roller 6 hrs $ 6705 $ 40230
Northwest Linings ea $ 14673 $ -
D5 Dozer 6 hrs $ 6205 1 $ 37230
SUBTOTAL $ 3,84710
OVERHEAD&PROFIT @ 21% $ 80789
TOTAL $ 4,65499
Verification of Hours Worked TOTAL $ 9,44386
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEET TOTAL: $ 9,443.86
Owner's Representative Date
Pay Estimate Entered
Date
By
FA Sheet No. 7
DAILY REPORT OF
FORCE ACCOUNT WORKED `- ENT
Project Name- SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/14/2013
Description of Work Import Screenings, Place in slope
Remove unsuitable
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor.
°LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 4 628 $ 25120
Rick/Kenny/Shane Operator Excavator 12 60 51 $ 72612
Kelly/Lloyd/Jerry Truck Dnverr 54 83 $ -
Dennls C Foreman 4 628 $ 251 20
Dominic E Pipe layer 4 4898 1 $ 19592
SUBTOTAL-LABOR $ 1,42444
LABOR OVERHEAD&PROFIT @ 29% $ 41309
LABOR TOTAL $ 1,83753
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs I Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 4 2873 $ 11492
335-1041121 GMC Truck 41 1646 $ 6584
220-143 300 excavator 41 17943 $ 71772
205-141 JD 310 backhoe 41 3889 $ 15556
Dump Truck and trailer 9541 $ -
SUBTOTAL-EQUIPMENT $ 1,05404
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 22135
EQUIPMENTTOTAL $ 1,27639
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units I Unit Price DOLLAR AMOUNT
Export loads $ 7500 $ -
Carbon CanyonfT barger/RL clearing 195 hrs $ 13000 $ 2,53500
Mini excavator/Bomag Roller 4 hrs $ 6705 $ 26820
Northwest Linings ea $ 14673 $ -
D5 Dozer 4 hrs $ 6205 1 $ 24820
SUBTOTAL $ 3,05140
OVERHEAD&PROFIT @ 21% $ 64079
TOTAL $ 3,692.19
Verification of Hours Worked TOTAL $ 6,805 11
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEET TOTAL: $ 6,805.11
Owners Representative Date
Pay Estimate Entered
Date
By
FA Sheet No.. 8
DAILY REPORT OF
FORCE ACCOUNT WORKED ENT
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/15/2013
Description of Work Import Screenings, Place in slope
Remove unsuitable
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 5 628 $ 31400
Rick/Kenny/Shane Operator Excavator 15 6051 $ 90765
Kelly/Lloyd/Jerry Truck Driverr 5483 $ -
Dennis C Foreman 5 628 $ 31400
Dominic E Pipe layer 5 4898 1 $ 24490
SUBTOTAL-LABOR $ 1,78055
LABOR OVERHEAD&PROFIT @ 29% $ 51636
LABOR TOTAL $ 2,29691
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 5 2873 $ 14365
335-104/121 GMC Truck 5 1646 $ 8230
220-143 300excavator 5 17943 $ 89715
205-141 JD 310 backhoe 5 3889 IS 19445
JD135 excavator 5 6711 $ 33555
SUBTOTAL-EQUIPMENT $ 1,65310
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 34715
EQUIPMENT TOTAL $ 2,00025
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Export 12 loads $ 7500 $ 90000
Carbon CanyonrF barger/RL clearing 6625 hrs $ 13000 S 8,61250
Mini excavator/Bomag Roller 5 hrs $ 4188 $ 20940
Northwest Linings ea $ 14673 $ -
D5 Dozer 5 hrs $ 6205 1 $ 31025
SUBTOTAL $ 10,03215
OVERHEAD&PROFIT @ 21% $ 2,106 75
TOTAL $ 12,138 90
Verification of Hours Worked TOTAL $ 16,436 06
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEETTOTAL• $ 16,436.06
Owners Representative Date
Pay Estimate Entered
Date
By
® 2\Z-
FA Sheet No.: 9
DAILY REPORT OF
FORCE ACCOUNT WORKED -�E_ T
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date. 10/16/2013
Description of Work Import Screenings, Place in slope
Remove unsuitable
Work by Subcontractor?. No
Prime Contractor. SCI Sub-Contractor
" LABOR
v
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff S Foreman 628 $ -
Rick/Kenny/Shane Operator Excavator 16 6051 $ 96816
Kelly/Lloyd/Jerry Truck Driverr 5483 $ -
Dennis C Foreman 8 628 $ 50240
Dominic E I JPipe layer 8 4898 $ 39184
SUBTOTAL-LABOR $ 1,86240
LABOR OVERHEAD&PROFIT @ 29% $ 540 10
LABOR TOTAL $ 2,40250
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325A08 F-450 2873 $ -
335-104/121 GMC Truck 8 1646 $ 13168
220-143 300 excavator 8 17943 $ 1,435 44
205-141 JD 310 backhoe 3889 $ -
JD135 excavator 8 6711 1 $ 53688
SUBTOTAL-EQUIPMENT $ 2,10400
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 44184
EQUIPMENT TOTAL $ 2,54584
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLARAMOUNT
Import 14608 loads $ 1 50 $ 21912
Carbon Canyonfr bargerIRL clearing 475 hrs $ 13000 $ 61750
Mini excavator/Bomag Roller 8 hrs $ 4188 $ 33504
Northwest Linings ea $ 14673 $ -
D5 Dozer 8 hrs I $ 6205 $ 49640
SUBTOTAL $ 1,66806
OVERHEAD&PROFIT @ 21% $ 35029
TOTAL $ 2,01835
Verification of Hours Worked TOTAL $ 6,96669
12%MARKUP (far prime when
subcontract work) $ -
contractor's Representative Date SHEET TOTAL- $ 6,96669
Owners Representative Date
Pay Estimate Entered
Date
By
FA Sheet No: 10
DAILY REPORT OF � ��
FORCE ACCOUNT WORKED ✓ICETIT
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/17/2013
Description of Work Hand seed slope/Place Jute mating
Work by Subcontractors No
Prime Contractor SCI Sub-Contractor
WWVMPV01011,1111110111?� FA- BOR et�nr`" t4 s ems -
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Jeff Foreman 628 $ -
RICk/Kenny/Shane Operator Excavator 16 6051 $ 96816
Kelly/Lloyd/Jerry Truck Dnverr 5483 $ -
Dennis C Foreman 8 628 $ 50240
Dominic E Pipe layer 8 4898 $ 39184
SUBTOTAL-LABOR $ 1,86240
LABOR OVERHEAD&PROFIT @ 29% $ 540 10
LABOR TOTAL $ 2,40250
EQUIPMENT 1 V-
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 2873 $
335-1041121 GMC Truck 8 1646 $ 13168
220-143 300 excavator 17943 $ -
205-141 JD 310 backhoe 3889 $ -
J0135 excavator 67 11 $
SUBTOTAL-EQUIPMENT $ 13168
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 2765
EQUIPMENTTOTAL $ 15933
MATERIALSISERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLARAMOUNT
Home depot#217172/4025216 1 ea $ 17971 $ 17971
Northwest Linings 1 ea $ 1,84000 $ 1,84000
$
SUBTOTAL $ 2,019 71
OVERHEAD&PROFIT @ 21% $ 42414
TOTAL $ 2,443.85
Verification of Hours Worked TOTAL $ 5,00568
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEET TOTAL: $ 5,005.68
Owner's Representative Date
Pay Estimate Entered.
Date
By.
0K
✓ FA Sheet No - 11
DAILY REPORT OF
FORCE ACCOUNT WORKED _ T
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/18/2013
Descnption of Work Hand seed slope/Place Jute mating
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor
k 10, wed rLABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Billie Joe/Marglt Laborer 16 4811 $ 76976
Rick/Kenny/Shane Operator Excavator 16 6051 $ 96816
Kelly/Lloyd/Jerry Truck Driverr 5483 $ -
Dennls C Foreman 8 628 $ 50240
DominicE Pipe layer 8 4898 1 $ 39184
SUBTOTAL-LABOR $ 2,63216
LABOR OVERHEAD&PROFIT @ 29% $ 763 33
LABOR TOTAL $ 3,39549
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 2873 $
3 3 5-1 0411 2 1 GMC Truck 8 1646 $ 131 68
220-143 300 excavator 17943 $
205-141 JD 310 backhoe 3889 $ -
D5 Dozer 8 6205 $ 49640
SUBTOTAL-EQUIPMENT $ 62808
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 131 90
EQUIPMENT TOTAL $ 75998
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Home depot#21717214025216 $
Northwest Linings 1 ea $ 1,60000 $ 1,60000
Is -
SUBTOTAL $ 1,60000
OVERHEAD&PROFIT @ 21% $ 33600
TOTAL $ 1,93600
Verification of Hours Worked TOTAL $ 6,091 47
12%MARKUP (for prime when
subcontract work) $ -
contractor's Representative Date SHEETTOTAL• $ 6,091.47
Owner's Representative Date
Pay Estimate Entered
Date
By.
FA Sheet No, 12
DAILY REPORT OF
FORCE ACCOUNT WORKED EN_ T
Project Name- SR 516 to 231st Levee Project No. 09.-3006
Item No Date 10/21/2013
Description of Work Regrade slope on west side of Levee
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor
Y-
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION His Hourly Rate Hrs OT Rate AMOUNT
Billie Joe/Margit Laborer 4811 $ -
Rick/Kenny/Shane Operator Excavator 10 6051 $ 60510
Kelly/Lloyd/Jerry Truck Driverr 5483 $
Dennis C Foreman 5 628 $ 31400
Dominic E Pipe layer 5 .4898 $ 24490
SUBTOTAL-LABOR $ 1,16400
LABOR OVERHEAD&PROFIT @ 29% $ 33756
LABOR TOTAL $ 1,501 56
EQUIPMENfk`
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description His Hourly Rate His Standby Rate AMOUNT
325-108 F-450 2873 $
3 3 5-1 0 411 21 GMC Truck 5 1646 $ 8230
220-143 300 excavator 5 17943 $ 89715
205-141 JD 310 backhoe 3889 $
135 Excavtor 5 57 11 $ 33555
SUBTOTAL-EQUIPMENT $ 1,31500
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 27615
EQUIPMENTTOTAL $ 1,59115
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $
TOTAL $
Verification of Hours Worked TOTAL $ 3,09271
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEETTOTAL: $ 3,092.71
Owner's Representative Date
Pay Estimate Entered
Date
By.
FA Sheet No : 13
DAILY REPORT OF
FORCE ACCOUNT WORKED
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/22/2013
Description of Work Shoulder drains and rock
Work by Subcontractor? NO
Prime Contractor SCI Sub-Contractor
fik ., �- r ,. _ "rxtm• .k _ " ':s" �.wa2w" '�''t'r`4�. " "".A"? '. % r
'* LABOR
°A4r
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Billie Joe/Mar It Laborer 4811 $
Rick/Kenny/Shane Operator Excavator 12 6051 $ 72612
Kelly/Lloyd/Jerry Truck Driverr 55 5388 $ 29634
Dennis C Foreman 6 62 8 $ 37680
Dominic E Pipe layer 6 4898 $ 29388
SUBTOTAL-LABOR $ 1,69314
LABOR OVERHEAD&PROFIT @ 29% $ 49101
LABOR TOTAL $ 2,18416
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
325-108 F-450 2873 $ -
335-104/121 GMC Truck 6 1646 $ 9876
220-143 300 excavator 6 17943 $ 1,07658
205-141 Dump truck 55 8084 $ 44462
135 Excavtor 6 6711 $ 40266
SUBTOTAL-EQUIPMENT $ 2,02262
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 42475
EQUIPMENT TOTAL $ 2,44737
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units I Unit Pnce DOLLAR AMOUNT
Northwest Linings 1 ea $ 11600 $ 11600
SUBTOTAL $ 11600
OVERHEAD&PROFIT @ 21% $ 2436
TOTAL $ 14036
Verification of Hours Worked TOTAL $ 4,771 88
12%MARKUP (for prime when
subcontract work) $ -
Contractor's Representative Date SHEET TOTAL: $ 4,771.88
Owners Representative Date
Pay Estimate Entered
Date
By
FA Sheet No: 14
DAILY REPORT OF
FORCE ACCOUNT WORKED NT
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/23/2013
Description of Work Shoulder drains and rock grading and Install
Regrade west Slope
Work by Subcontractor? NO
Prime Contractor SCI Sub-Contractor
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Billie Joe/Marglt Laborer 4811 $ -
RICk/Kenny/Shane Operator Excavator 16 6051 s 96816
Kelly/Lloyd/Jerry Truck Driverr 8 5483 $ 43864
Dennis Foreman 8 628 IS 50240
Dominic Pipe layer 848981 $ 39184
SUBTOTAL-LABOR $ 2,301 04
LABOR OVERHEAD&PROFIT @ 29% $ 66730
LABOR TOTAL $ 2,96834
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
Mini Excavator 8 25 17 $ 201 36
335-104/121 GMC Truck 8 1646 $ 13168
220-143 300 excavator 3 17943 $ 53829
205-141 Dump Truck 8 8084 $ 64672
135 Excavtor 8 6711 $ 53688
SUBTOTAL-EQUIPMENT $ 2,05493
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 43154
EQUIPMENT TOTAL $ 2,48647
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Icon 1 ea $ 13651 $ 13651
Trader 2 hrs S 1457 $ 29 14
D5 Dozer 2 hrs $ 6205 $ 12410
$
SUBTOTAL $ 28975
OVERHEAD&PROFIT @ 21% $ 6085
TOTAL $ 35060
Verification of Hours Worked TOTAL $ 5,80541
12%MARKUP (for prime when
subcontract work) $ -
Contractors Representative Date SHEET TOTAL- $ 5,805.41
Ovmer's Representative Date
Pay Estimate Entered,
Date
By
t
FA Sheet No 23
DAILY REPORT OF
FORCE ACCOUNT WORKED _T
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/22/2013
Description of Work Hydro seed
Work by Subcontractor? yes
Prime Contractor SCI Sub-Contractor Terra Dymanincs
LABOR a ep
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Tally H Seeder 3 2937 $ 88 11
Marganto Seeder 3 2994 $ 8982
$
$
SUBTOTAL-LABOR $ 17793
LABOR OVERHEAD&PROFIT @ 29% $ 5160
LABOR TOTAL $ 22963
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
1998 Kenworth t-800 3 11290 $ 338 70
SUBTOTAL-EQUIPMENT $ 33870
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 7113
EQUIPMENT TOTAL $ 40983
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Seed 170 Ibs $ 1 55 $ 26350
fertilizer 8 bags $ 1725 $ 138 00
Rainer Fiber mulch 40 bags $ 7 50 $ 30000
PT Tar 60 Ibs $ 060 $ 3600
SUBTOTAL S 737 50
OVERHEAD&PROFIT @ 21% $ 154 88
TOTAL $ 89238
Verification of Hours Worked TOTAL $ 1,531 74
12%MARKUP (for prime when
subcontract work) $ 18381
Contractors Representative Date SHEETTOTAL: $ 1,715.55
Owner's Representative Date
Pay Estimate Entered,
Date
By
FA Sheet No : 15
DAILY REPORT OF
FORCE ACCOUNT WORKED I" ,T
Project Name SR 516 to 231st Levee Project No 09.-3006
Item No Date 10/24/2013
Description of Work Install Jute Matting, Hand seed
Regrade levee to
Work by Subcontractor? No
Prime Contractor SCI Sub-Contractor
ti-c*'T'R,c ,x--.�ae.�xa.-.,�,�a�,•LABOR ,r�r�. r�dTs��`T�iL��",4','.€c'�'",ai�i.��.�.��,�*�
STRAIGHT TIME OVERTIME 7DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Casey M/Billie Joe Laborer 121 4811 $ 57732
Rick/Kenny/Shane Operator Excavator 18 6051 $ 1.08918
Kelly/Lloyd/Jerry Truck Driverr 65 5388 $ 35022
Dennis C Foreman 6 628 $ .37680
Dominic E Pipe layer 6 4898 $ 29388
SUBTOTAL-LABOR $ 2,68740
LABOR OVERHEAD&PROFIT @ 29% $ 77935
LABOR TOTAL $ 3,46675
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description His Hourly Rate Hrs Standby Rate AMOUNT
Mini Excavator 61 2517 $ 15102
335-104l121 GMC Truck 6 16 46 $ 9876
220-143 300 excavator 17943 $ -
205-141 Dump Truck 65 8084 $ 52546
135 Excavtor 8 67 11 $ 53688
SUBTOTAL-EQUIPMENT $ 1,31212
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 27555
EQUIPMENT TOTAL $ 1,58767
MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$
Trader hrs $ 1457 $ -
D5 Dozer 3 hrs $ 6205 $ 186 15
Bomag Roller 3 hrs $ 4188 $ 12564
SUBTOTAL $ 31179
OVERHEAD&PROFIT @ 21% $ 6548
TOTAL $ 37727
Verification of Hours Worked TOTAL $ 5,43169
12%MARKUP (for prime when
subcontract work) $ -
contractor's Representative Date SHEET TOTAL: $ 5,431.69
Owner's Representative Date
Pay Estimate Entered.
Date
By.