HomeMy WebLinkAboutPW13-103 - Change Order - #07 - Goodfellow Bros., Inc. - SE 256th St Improvements - 01/02/2014 Records Man-V �-gemient
KENTDocument
WASHINGTON -
Rf
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: Goodfellow Brothers, Inc
Vendor Number:
ID Edwards Number
Contract Number: PW
This is assigned by City Clerk's Office
Project Name: SE 256t" St Improvements
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 6/6/2013 Termination Date:
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Phil McConnell Department: PW-Engineering
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change order #7 & 8 __ ___
5 Pubhc\RecordsManagement\Forms\ContractCover\adcc7832 1 11/08
000000
74
KENT
WASHINGTON
CHANGE ORDER NO. #7
NAME OF CONTRACTOR: Goodfellow Brothers. Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SE 2561" Street Improvements
ORIGINAL CONTRACT DATE: June 6, 2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Remove and dsipose of trees in conflict with joint trench; not shown on
plans to be removed.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,208,988.60
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $18,019.92
(rncl. applicable WSST)
Current Contract Amount $5,227,008.52
(incl. Previous Change Orders)
Current Change Order $6,660.09
Applicable WSST Tax on this Change $632.71
Order
Revised Contract Sum $5,234,301.32
CHANGE ORDER - 1 OF 3
Original Time for Completion 300 working days
(insert date)
Revised Time for Completion under 302 working days
prior Change Orders
(insert date)
Days Required (t) for this Change 0 calendar days
Order
Revised Time for Completion 302 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written beloT14
CONTRACTOR: CITY OF KENT:
By Bv-
rr441 ( nature) CCU ( nat re)
Print Print Name: «Uy a 4!�a,?(4
Its Vt�r,_* VAc,ax�_f Its_
(tltr ) (tla )
DATE: j� I l`I DATE:
CHANGE ORDER - 2 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
I
CHANGE ORDER - 3 OF 3
��� FILE NO: 200.2
KENT
CHANGE ORDER WORKSHEET NO. 7
Construction Management Division — Public Works
Project: SE 256th Street Improvements Project No.: 09-3012C
Project Engineer: Mark Madfai Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: Goodfellow Brothers
Date: 10/29/2013
I. PROPOSED CHANGE
Remove and dispose of trees
II. REASON AND BACKGROUND FOR CHANGE
Trees In conflict with joint trench; not shown on plans to be removed
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ❑ Not Applicable
Change Order No. j FOR ACCOUNTING USE ONLY
Sch No Item'Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
6 tree removal and disposal to 1 1 CS $6,660.09 $6,660.09
I facilitate joint trench ------- ---- _ _._
I '
® 1 Independent Estimate Attached CREATE PAY ITEM ONLY — Payment to be made ® PAY THIS PAY ESTIMATE
-REQUIRED at a later date upon completion-of work _ _
Material Submittals Reauired — CC construction Coordinator New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No, B I. No Item Description Qty Unit I Unit Price cost of Item
-- -- ---- - - - - - -- - - ----
Independent Estimate Attached - REQUIRED
INCREASE/DECR EASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. - I FOR ACCOUNTING USE ONLY
Sch No B I No Item Description _.-Qty Unit Unit Price Cost of Item
._-_ . -------
Independent Estimate Attached - REQUIRED EJ
1 REV. DATE-4/01/10
Y
r
FILE NO: 200.2
KENT
TOTAL ESTIMATED COST OF CHANGE ORDER $6,660.09
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $6,660.09
IV. WORKING DAYS
Original Contract 1300 Due This Change Order* Previous Total 302
DATE: -L ' -- — ---- - - - ----- - -
* -UgIgpqtIgnijUstification Re uired: not on critical path
TOTAL WORKING DAYS* ca"L
*This Change order t Previous Total
All work, materials and measurements to be In accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: P i cCon II 1. -i Date:
i
Construction Supervisor: Date: �I
Construction Manager: Pau l _ Date:
i
2 REV.DATE:4/01/10