CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: Titan Earthwork, LLC
Vendor Number:
JD Edwards Number q
Contract Number: ''VV IZ? 1 1�
This is assigned by City Clerk's Office
Project Name: 1121h Ave SE Watermain
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 7/29/2013 Termination Date:
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Department: Public Works Engineering
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change order #2
S Public\RecordsManagement\Forms\ContractCover\adcc7832 1 11/08 ,
KEN T
WASHINGTON
CHANGE ORDER NO, #2
NAME OF CONTRACTOR: TITAN Earthwork, LLC ("Contractor")
CONTRACT NAME & PROJECT NUMBER: 112th Ave Se Watermain
ORIGINAL CONTRACT DATE: 7/29/2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
and b mutual consent of the parties, the project contract is modified as follows:
considerationy p J
Agreement, entitled "Description of Work, is hereby modified to
1. Section I of the g p
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Fabricate and install overflow support for Blue Boy tank to meet
Department of Health requirements.
2. The contract amount and time for performance provisions of Section II Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $1,811,541.01
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $7,227.00
(Incl. applicable WSST)
Current Contract Amount $1,818,768.01
(incl. Previous Change Orders)
Current Change Order $6,500.00
Applicable WSST Tax on this Change $617.50
Order
Revised Contract Sum $1,825,855.51
CHANGE ORDER - 1 OF 3
Original Time for Completion 120 working days
(insert date)
Revised Time for Completion under 0
prior Change Orders
(insert date)
Days Required (f) for this Change 0 calendar days
Order
Revised Time for Completion 120 working days
(Insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below aA
CONTRAC R: CITY O KENT:
By: `� "C By: 4
signature11 , (signature)
Print Name: 12Ck3 14iKESO Print Name: Tim
Its N�'v.;l{c.1 A-44,vaf ,Cle Its BQu Ol�c, W oy�Icy i�lcc-trx-- _
(titled / itle)
DATE: /-'{ DATE:
CHANGE ORDER - 2 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
CHANGE ORDER - 3 OF 3
FILE 200 2
CHANGE ORDER WOR.KSHE ET
Date of change order: / t° /z Date worked performed: / z�'�'s
Concurrence/Approval(coos&Date): Construction Supervisor Construction Manager
Project Name: /'- Y-r-Project Number. e�, /����s'"'
Contractor: "T/T�iy'i�✓ .`� �X
C.O. Type/Bid Item#: Force Account(est. total)$ Lump Sum$
Schedule#: Change Order#:
Ordered By: o/ rti��zLr-- Engineers ,�'�f '�+- Contractor / 1 � '�
Description of Work: °���
Reason: ?z saca u,-u�S
COST ESTIMATE
X $ rfx S tics, G S = $ S`•C��� "�
QUANTITY PRICE UNIT(S) ESTIMATED TOTAL
ACTUAL COST_
� x $ l�cx) G s = $
rys� c
QUANTITY PRICE UNIT(S) ACTUAL TOTAL
TIME
Extension Of Contract Time Due To This Change Order-------------------Calendar/Working Days__
COMMENTS