HomeMy WebLinkAboutAD07-220 - Amendment - #2 - Engineering Economics, Inc. - Events Center LEED Consultant - 04/22/2009 00000*4
KENT
AMENDMENT NO. 2
NAME OF CONSULTANT OR VENDOR: Engineering Economics Inc.
CONTRACT NAME & PROJECT NUMBER: Kent Events Center Proiect
ORIGINAL AGREEMENT DATE: August 15. 2007
This Amendment is made between the City and the above-referenced Consultant or Vendor and
amends the original Agreement and all prior Amendments All other provisions of the original Agreement
or prior Amendments not inconsistent with this Amendment shall remain in full force and effect. For
valuable consideration and by mutual consent of the parties, Consultant or Vendor's work is modified as
follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, the Consultant or Vendor shall:
Perform additional commissioning services at the Kent Events Center to comply
with the requirements of Puget Sound Energy's New Construction Commissioning
Grant program in accordance with the attached and incorporated Exhibit A.
Work will be billed on a time and materials basis, not to exceed $12,847.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are modified as follows
Original Contract Sum, $83,774.00
including applicable WSST
Net Change by Previous Amendments $12,650.00
including applicable WSST
Current Contract Amount $96,424.00
including all previous amendments
Current Amendment Sum $12,847.00
Applicable WSST Tax on this Amendment $0.00
Revised Contract Sum $109,271.00
Original Time for Completion December 31, 2009
(insert date)
Revised Time for Completion under December 31, 2009
prior Amendments
(insert date)
Add'I Days Required (f) for this 0 calendar days
Amendment
Revised Time for Completion December 31, 2009
(insert date)
AMENDMENT- 1 OF 2
w R
4
In accordance with Section VII of the Agreement, the Consultant or Vendor accepts all
requirements of this Amendment by signing below, by its signature waives any protest or claim it may
have regarding this Amendment, and acknowledges and accepts that this Amendment constitutes full
payment and final settlement of all claims of any kind or nature arising from or connected with any work
either covered or affected by this Amendment, including, without limitation, claims related to contract
time, contract acceleration, onsite or home office overhead, or lost profits. This Amendment, unless
otherwise provided, does not relieve the Consultant or Vendor from strict compliance with the guarantee
and warranty provisions of the original Agreement.
All acts consistent with the authority of the Agreement, previous Amendments (if any), and this
Amendment, prior to the effective date of this Amendment, are hereby ratified and affirmed, and the
terms of the Agreement, previous Amendments (if any), and this Amendment shall be deemed to have
applied.
The parties whose names appear below swear under penalty of perjury that they are authorized to
enter into this Amendment, which is binding on the parties of this contract.
IN WITNESS, the parties below have executed this Amendment, which will become
effective on the last date written below.
CONSULTANT/VENDOR: CITY OF KENT:
By: By:
(signature) at re
Print Name: Jeffrey Nichols Prl Na e:
Its Branch Manager j
(title) (title)
DATE: April a, 2009 DATE:
APPROVEO AS TO FORM:
(applicable if amendment requires mayor's signature)
Vvv bv , L--,,
Keril Law Department
AMENDMENT- 2 OF 2
`4
Kent Events Center
Amendment #2 to EEI Contract
EXHIBIT A: SCOPE OF WORK
1) The Consultant shall complete the following work requirements for PSE Commissioning Grant:
a) Confirm existing commissioning scope conforms to Washington State Energy Code (WSEC)
b) Confirm building was commissioned using BCA practices
c) Confirm building has been commissioned per EEI's contract, all scopes described in contract have been
completed
1) SOJ to provide EEI payment documents if required (work scopes complete, payments made)
d) Review submittals and verify in the field the following
1) Windows Take a 15% sampling of total window areas Sampling should be of storefront, small suite
windows in hallways, and office windows
a) Confirm based on approved submittals and Manufacturer's Rep input that submitted windows
were installed per contract
b) Confirm windows' SHGC and U-value match submittals and conforms to Washington State
Energy Code(if available, provide documentation from manufacturer to confirm make/model of
glazing and that required values were met or exceeded)
2) Shell Insulation Report on the shell insulation level using thermal insulation imaging Take readings
of each side of the building to confirm compliance with energy code and that insulation was installed
per contract Identify significant"hot" spots, if any, that require further investigation
3) HVAC Equipment Confirm based on approved submittals and physical inspection that submitted
equipment was installed per contract
4) Lighting Power Density Confirm using fixture counting and calculations that the LPD is as specified
in the plans 15% sampling of office area, concourse, BOH, and Bowl
5) Envelope Sealing Review 15% of the envelope and confirm that the sealing of any building
penetrations has been completed Photograph these installations
6) Duct Sealing Confirm duct sealing was verified through physical inspection and duct leakage testing
during installation Photograph these installations
7) Confirm w/ Electrical Engr if any daylight sensing equipment is installed in the facility If equipment is
installed, confirm w/tests that the equipment is operating as specified (15%sampling acceptable)
e) Provide PSE copy of all mechanical FPT's that were completed on the protect and confirm tested
equipment is operating as described by the manufacturer Include trending verification
f) Review TAB report and confirm equipment is operating per intended design Use a 10% sampling rate
Include refrigeration system brine and refrigerant flows in addition to HVAC airflows
g) Verify that mechanical equipment matches approved submittal and the FPT has been completed and the
equipment is operating as described by the manufacturer Also, sample 15% of lighting and occupancy
controls and confirm equipment matches approved submittal and the FPT has been completed and the
equipment is operating as described by the manufacturer
h) EEI to provide a copy of the"Issues List" used through-out the protect that details"major" (major meaning
issues that impact energy use) issues only and shows that these issues have been resolved and
confirmed complete by EEI
2) The Consultant shall complete the following reporting and documentation requirements for PSE
Commissioning Grant:
a) SOJ to provide a copy of EEI's Cx contract w/City of Kent that includes work scope and fee In addition,
PSE grant scope amendment should be included in this documentation
b) EEI to provide a copy of the Cx Plan that includes site visit installation verification reports and FPT's and
their results(see item 1 e" above)
REQUEST FOR MAYOR'S SIGNATURE
N-147 KENT Please Fill in All Applicable Boxes
WASMINGTON
Routing Information (ALL REQUESTS MUST FIRST BE ROUTED THROUGH THE LAW DEPARTMENT)
Oiiginato�t�f, -b4e� Phone (Originator)- b ' 0 a
Date Sent Lfl I� I)G Date Required:
Return Signed Document to tit ` 11cC,,, CONTRACT TERMINATION DATE:
VENDOR NAME: ��L_� DATE OF COUNCIL APPROVAL:
Brief Explanation of Document-
All Contracts Must Be Routed Through the Law Department
(This Aoea to be Completed 6y the Law Department)
Received: v `'J
APP
Approval of Law Dept.: City of Kent
Law Dept. Comments Office of the Mayor
Date Forwarded to Mayor:
Shaded Areas to Be Completed by Administration Staff
Received:
Recommendations & Comments:
r
Disposition:
Date Retuined:
Iage5870 31,05