CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission to City Clerks Office. All
portions are to be completed, if you have questions, please contact Mary Simmons, City
Clerks Office.
Vendor Name: �� ✓�Q 4Y xx
A`
Contract Number:
Thie le by AA�r%r Cim mnne
•.n. ..r vw•y.w� v� . .�.� vn.n..v .a
Vendor Number: 5—1 l 5
Ji^ r I
Project Name:
Contract Effective Date:
Contract Termination Date: / Z
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager:
Department:
Abstract:
ADCL7832 07/02
KENT
WASH IN GTGN
CHANGE ORDER NO. 1
NAME OF CONTRACTOR, CONSULTANT, OR VENDOR Geomatrix ("Contractor")
CONTRACT NAME& PROJECT NUMBER: Town Square Plaza - Geomatrix
ORIGINAL CONTRACT DATE. August 6, 2007
This Change Order amends the above-referenced contract; all other provisions of the contract that are
not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual
consent of the parties, the project contract is modified as follows
1. Section I of the Agreement, entitled "Description of Work," is hereby modified as follows-
Provide all labor, materials, and equipment necessary to:
Remove and sample contaminated soil stockpile at the Town Square Plaza as
described in the Consultants proposal dated August 23, 2007 attached and
incorporated as Exhibit A
2. The contract amount and time for perfonnance provisions of Section II "Compensation," and
Section III, "Time for Completion," are hereby modified as follows-
Original Contract Sum, $ 79100.00
including applicable alternates and WSST.
Net Change by Previous Change Orders $ 0.00
(incl applicable WSST)
Current Contract Amount $ 79100.00
(incl Previous Change Orders)
Current Change Order $ 4,422.86
Applicable WSST Tax on this Change Order $ 0.00
Revised Contract Sum $115522.86
Original Time for Completion 12/31/07
(insert date)
Revised Time for Completion under NA
prior Change Orders
(insert date)
Days Required ± for this Change Order 0
Revised Time for Completion 12/31/07
(insert date)
Pursuant to Section XIII - F, entitled "Modification," of the Contract executed by the parties, the
Contractor accepts all requirements of this Change Order by signing below Also, pursuant to the above-
referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and
acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including, without
limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits.
The parties whose names appear below swear under penalty of perjury that they are authorized to enter
into this contract modification, which is binding on the parties of this contract
3. The Contractor will adjust the amount of its performance bond (if any) for this project to be
consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement,which will become effective on the
last date written below.
CONTRACTOR: CITY OF KENT:
By:�S Q.T�L�ii�c� _�� By:
(signature) (signature)
Print Name:46'eA/"r,A�4*=dd ,an., Print Name: Jeff Watling
Its eT�-''A r 0 Its Director
o (Title)
DATE: /U DATE: t It an l
APPROVED AS TO FORM:
Kent Law Department
Town Square Plaza—Geomatnx CW1
CONTRACT MODIFICATION-2 OF 2
Geomatrix
August 23, 2007
Mr. Perry Brooks
Park& Open Space Planner
City of Kent
220 Fourth Avenue S.
Kent, WA 98032-5895
Subject: Proposed Supplemental Agreement for Additional Contaminated Soil
Assistance,N.2nd Ave. & Smith St.
Dear Mr. Brooks:
Geomatrix Consultants, Inc. (Geomatrix)proposes to amend our existing scope of work
under the Consultant Services Agreement (PO #56438) to assist the City of Kent(the
City) with environmental compliance issues at City property on the SW corner of North
2nd Avenue and Smith Street. The proposed amendment is based on our understanding
that an additional 5 cubic yards of suspected contaminated soil has been excavated in the
course of installing Puget Sound Energy utilities to the new Town Square Plaza site. The
soil has been stockpiled on and covered by plastic to prevent migration of contaminants.
We will refer to this as the third stockpile.
Scope of Work:
The following tasks will be completed by Geomatrix under this scope of work:
1. Collected a sample of the third stockpile for characterization of gasoline and
diesel contamination, volatile organic compounds, and polychlonnated biphenyls
(PCBs). Geomatrix will have the samples analyzed at the Analytical Resources,
Incorporated (ARI) laboratory on a standard(14-day) turnaround basis.
2. Communicate the results of the analyses to the City and Waste Management, Inc.
(WMI)for a waste profile by WMI. Geomatnx will contract with WMI to haul
the soil for disposal (depending on the Waste Profile assigned by WMI,this may
be to the Alaska Street transfer station in Seattle, for ultimate disposal of the soil
at a Subtitle D landfill). If WMI concludes that the soil is compatible with the
existing waste profile for the first stockpile, then Geomatrix will ensure that WMI
hauls and disposes of the stockpile at the same time as the first stockpile. If the
soil is not compatible with the first stockpile, a minimum 30-ton hauling/disposal
charge by WMI will apply. The City of Kent will be responsible for loading the
soil onto the WMI trucks at a mutually-agreeable time.
3. Geomatrix will incorporate the third stockpile information into the brief
environmental report covering the sampling of both stockpiles, analytical results,
and final disposition of the contaminated soil and submit one copy each, to the
City and the Washington State Department of Ecology.
One Union Square,600 University Street.Suite 1020 Tel 206 342 1760 w geomatnx com
Seattle.Washington 98101-4107 Fax 206 342 1761
Mr. Perry Brooks Geomatrix
August 23 2007
Page 2 of 2
City of Kent Responsibilities:
For the purposes of this proposal, scope of work, and budget, we assume that:
• All necessary permits are in place and the City will transfer the permits to
Geomatrix, as needed;
• The City will manage the actions of other contractors involved in the pile
disposal, and any traffic control planning and implementation on this project; and
• The City will issue all necessary notifications (e.g. water service shut down) and
coordinate all necessary activities with other parties
Schedule:
To expedite the soil removal, Geomatrix will sample the third stockpile on Friday,
August 24, 2007, based on verbal authorization from the City. We will await formal
approval of this amendment to the scope of work before proceeding further. The final
report will be completed within 3 weeks of receiving final analytical results, and weight
tickets from WMI regarding the final amount of soil disposed at the disposal facility.
Budget Estimate:
Our estimated additional budget to complete this work will not exceed $4,423.00, as
detailed in the enclosed Attachment 2. This budget includes the contingency that the
third stockpile must be removed in a separate trip by WMI (under a minimum 30-ton
charge, approximately$2075); if it does not, then the third stockpile may be compatibly
removed by WMI along with the first stockpile in one trip, at approximately$700
additional hauling/disposal cost. We will not exceed this budget without the City of
Kent's prior authorization. Any changes, new finds, or other factors outside our scope of
work or conditions that may increase the cost above the proposed budget will be brought
to the attention of the City. We will invoice based on time and materials in accordance
with the attached Schedule of Charges and Conditions (Attachment 3) and our pending
standard consultant Agreement.
We look forward to working with you on this project. Please call at 206/342-1760 if you
have any questions or require additional information.
Sincerely,
GEOMATRIX CONSULTANTS, INC.
Tim Reinhardt,CIH Kathleen Goodman, L.G., L.Hg.
Senior Scientist Principal Hydrogeologist
Attachments
1\Project\13591-City of Kent-2nd and Sm liM00-Admm\2nd and Smith Soil Stockpiles Third scope doc
Attachment 1
COST ESTIMATE
2nd and Smith Stockpile Characterization--Amendment 1: Third Stockpile Disposal
KENT, WASHINGTON
8/23/2007
Description Rate Units Sampling Consulting
Quantity Cost Quantity Cost TOTAL
LABOR
Pro3ect Manager $59 Hr 05 $29 50 05 $29 50
Senior Eng/Sci I1 $52 Hr 45 $234 00 25 $130 00
Senior Sci./Eng I $40 Hr 0 $0 00 0 $0 00
Sr Industrial Hygienist $52 Hr 0 $0 00 0 $0 00
Project Engineer $31 Hr $0 00 0 $0 00
Drafting/Graphics S28 Hr 0 %00 0 $0 00
Word Processing $16 Hr 0 $0 00 05 $8 00
Administrative $14 Hr 0 $0 00 1 5 $21 00
Subtotal labor 5 $263.50 4.5 $188.50 $452.00
LABOR+OH+ FEE 2.8388 $1,411.45
ODCs
Car Mileage $ 0 485 mi 46 $22 31 0 $0
Field Supplies $ 150 LS 1 $150 0 $0
Parking $ 1200 Day 1 $12 00 0 $0
PID $ 10000 Day 1 $100 00 0 $0
Histoncal Documents $ - LS 0 $0 00 0 $0
Subtotal $135.81 $0.00 $135 81
Markup 10 % $13 58 $0 00 S 13 58
SUBTOTAL S149.39 $0 00 $149 39
SUBCONTRACTORS
Analytical Laboratory
TPH-G/BTEX- Soil $80 Ea 1 $80 0 $0
VOCs $170 Ea 1 $170 0 $0
TPH-Dx-Soil $65 Ea 1 $65 0 $0
PCBs $110 Ea 1 $110 0 $0
Metals $125 Ea 1 $125 0 $0
Rush Charges 100% Ea 0 $0 0 $0
Analytical subtotal $0 $550
Waste Managementi $6286 ton 30 $1,886 0 $0 S1,886
0 $0 0 $0 $0
Subtotal WM and Lab $2,436 $0 $1,886
Subcontractor tax 8 8% $166
Markup on all subs 10 % $260
ODC SUBTOTAL $3,011.41
TOTAL $4,422.86
Costs for subcontractors based on following assumptions:
'Waste Management will haul and dispose of<=8 tons of petroleum contaminated soil,at$58 75/ton
plus 7%fuel surcharge and environmental fee, minimum 30 ton load.
does not include standby time($120/hr)in case of delay
Sales tax of$0 088 included in subcontractor prices
I\Project\13591-City of Kent-tad and Smith\0000-AdminWttachment 1 Budget Estimate--amendment 1 As