HomeMy WebLinkAboutPK04-217 - Change Order - #2 - Honeywell, Inc. - Public Works Shop Card Access System - 10/11/2002 Records M erne
KENT W A9NINOTON Document
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission to City Clerks Office. All
portions are to be completed, if you have questions, please contact Mary Simmons, City
Clerks Office.
Vendor Name: 4OwI-- u U)e- Vendor Number: �3 5 7 a
JD Edwards Number
Contract Number:
This is assigned by Mary Simmons Description: Ch -e L'< ke- Y 2N S�GU�v }eti� S 0pS
Detail: In S l oa 0 �r e e- r5 a-
Project Name: 0 ���, W e S 'LCu `� a 5 c� S k e u` P Cy S p o S
Contract Effective Date: I ! G Termination Date:
Contract Renewal Notice (Days): 3 a A S t) K& CA Q r_eY da te-
Number of days required notice for termination or renewal or amendment
Contract Manager: (1)k --,r L Department: -P0_Y ra s
Abstract:
s eA�a t,L c, r e av 0�
'P v S . ' ; s F Dct r t C> '� L/ -i .r C_ C i- kez S Ile e_vl
ADCL7832 07/02
KENT
CITY OF KENT PARKS, RECREATION & COMMUNITY SERVICES
CHANGE ORDER NUMBER 2
PROJECT NAME & NUMBER Installation of Honey well Security System at Shops
TO Howard Richardson, Honeywell
FROM Charles Lindsey, City of Kent Facilities
DATE. October 1, 2002
This Change Order shall only affect the terms indicated herein All other Contract provisions,which are not
inconsistent with this Change Order, shall remain in effect For valuable consideration and by mutual
consent of the parties, the modifications to the Contract are as follows
SCOPE OF CHANGE ORDER Provide all labor, materials, and equipment necessary to
1 Add five more doors and one controller to original agreement This includes materials and
labor $16,497 00
Section 2 and 3"Payment' and "Time for Completion" are modified as follows
Original Contract Sum w/o WSST $32,150 00
Previous Change Orders $10,425 00
Revised Contract Sum $42,575 00
Change Order#1 w/o WSST $16,497 00
Revised Contract Sum $59,072 00
On anal Contract Completion Days
Days Required for Completion t
Revised Project Completion Days ±
Pursuant to Section 7 "Changes" of the contract executed by the City of Kent April 1, 2002, the
Contractor accepts all requirements of this Change Order by signing where indicated below Also,
pursuant to the above-referenced contract provisions, Contractor agrees to waive any protest it may
have regarding this Change Order and acknowledges and accepts that this Change Order
constitutes full payment and final settlement of all claims of any kind or nature arising from or
connected with any work either covered or affected by this Change Order, including, without
limitation, claims related to contract time, onsite or home office overhead, or lost profits
Changeorderi honeywellshops 10101102
The parties whose names appear below swear under penalty of pegury that they are authorized to
enter into a contract modification that is binding on the parties of this contract
IN WITNESS WHEREOF, the parties have executed this Change Order on the day and year
written below
CONTRACTOR CITY O KENT
By,,, By
Name, Pnncipal Mayor
Date t (? ^ G 7 ^Q Z Date 1d -
Owner's signature represents authorization to proceed with modification.
Approved as to Form Attest y:
Tom Brubaker,Oe UtyrCity Attorney Brenda Jacober, City Jerk
Changeorderl honeywel lshops 10/01/02
FROM HONEYWEL.L FRX NO. : 2062366775 Sep. 17 2002 07.07AM P2
HONEYWELL CONTRACT RIDER
Add#
AGREEMENTNUMBER 722722-01-98813 2 DATE- 9/12102
This RIDER shall be attached to,and made a part thereof,the existing valid contract between (CONTRACTOR)
Honeywell International and(CUSTOMER) CITY OF KENT PUBLIC WORKS
Customer Location is at 5821 S 240TH STREET KENT WA
with all provisions of said contract to remain in force unless specifically modified herein this F IDER
ADDITIONAL PROTECTION
EQUIFNIENT
OTY ITEM LOCATION
1 STAR 1 CON OLLER
2 WIU BOARA
2 LARGE ENCLOSURES
1 POW RSUPPLYSMP•7CTX
7 READERS HID 6386 MINI PROX
1 REX DS150
1 MIRO BOARD 16/0
7 SINGLE D00R MT—ACTS
'—._ _...__.._._... -----
—-----------
—-----
---------.._. ....
7 WIRE
1 LIFT
This Rider shall not be binding upon the Contractor unless accepted in writing by an officer of the Contractor,and in the
event of failure of acceptance,the sole liability of the Contractor shall be to refund to the Subscriber the amount,if any,
that has been paid to the Contractor upon the signing of this Rider. The Subscriber hereby acknowledges receipt of a
copy of this Rider and acknowledges that they have read the terms and conditions thereof.
Installation Charge $16,497 00 Added Monthly Charge'_
Honeywell Representative HRICHARDSON jsMar:Sjg ure
Approved for Honeywell by Date
Date, Purchase Order P
Fda Nnmo CITY OF KENT 4H0P 9.12 AD xis